Construction and delivery timeline

April 2025
Archaeological works start before demolition
May 2025
Strip-out of retail units
Summer 2025
Shopmobilty moved to its new location
Summer-Autumn 2025
Gas, electricity and water utility works carried out around the Grafton Centre
Late 2025 - Early 2026
Demolition of Abbeygate House
Early 2026
Hotel construction starts
Early 2026
East Road public realm improvements start
December 2026
Retail loop construction starts
December 2026
Life science phase one construction starts
April 2027
New retail square opens to the public
November 2027
Hotel completion
Early 2028
Retail construction complete
2028-9
Life sciences phase one construction complete